Table VII.
TECHNICAL RESULTS OF THE WORKS FINANCED BY THE LABOUR FUND
IN 1934-35 1
Works executed by Organs other than the State (Autonomous Administrations;
Private Undertakings with the Participation of Public Administrations).
Nature of work
Technical results
Share
of the Labour Fund
in the costs
of construction
(%)
1. Roads and bridges :
(a) Paved roads and bridges
(b) Road surfaces
2. Railways and tramways :
(a) Railways
(b) Tramways
3. Waterways and ports
4. Fundamental improvements.
5. Water-supply work and water
mains
6. Electrification
7. Gas supplies
8. Construction :
(a) Public buildings .
(b) Dwelling-houses2
9. Other works
New roads : 249 kilometres.
Roads rebuilt: 20 kilometres.
New roads : 78.7 kilometres.
Railway lines : 20 kilometres.
Tramway lines : 1.1 kilometres.
Regulation of navigable rivers : 28 kilometres.
Regulation of rivers : 25.8 kilometres.
Drainage : 27.6 kilometres.
Special improvements : 5,708 hectares.
Canals : 74 kilometres.
Piping : 74 kilometres.
Inter-urban systems : 333.8 kilometres.
Low-tension lines : 28 kilometres.
Gas-supply systems : 41.6 kilometres.
Construction : 841,000 cubic metres.
Construction : 71,000 cubic metres.
Adaptation and consohdation of building
lands of an area of 394,000 square metres.
57-3
77.2
64-3
51-8
69.4
87-3
70.2
69.5
44-7
61.9
82.6
65.0
1 From April 1st to December 31st, 1934.
2 Including the adaptation of building lands.

Images and transcriptions on this page, including medium image downloads, may be used under the Creative Commons Attribution 4.0 International Licence unless otherwise stated. Creative Commons Attribution 4.0 International Licence